Site Establishment

Suggested plant and equipment requirements for Insitu-Asphalt


(+/- 350 m2/day output plus a team of 20 workers)

4 × wheel barrows
10 × spades (flat garden style, not rounded shovels)
6 × containers (25 liter)
1 × broom
2 × hammer (plus 4” concrete nails and fish line)
2 × thickness guides
(30 mm angle iron × 30 m long)
3 × metal rakes
3 × watering cans
1 × 4 m level
1 × vibratory pedestrian roller (or hand tampers if required)
1 × 500 – 1000 liter water tank
1 × drum stand
1 × drum tap

(excluding spares in case of breakages and all relevant safety signs and devices)

A pictoral representation of how the plant and equipment is utilised can be found at our Labour Based Aspalt Tasks page while pictures showing the high level of the labour component are on the Labour Intensive Asphalt Construction page or you might like to get a free copy of the Labour Based Insitu-Asphalt Quantities & Costs Estimator to help with estimating materials quantities and costs for your project.